Canadawide Project: Refrigeration for Warehouses and Packaging Rooms
This project involved delivering a refrigeration system in record time, in coordination with the complete renovation of the building. The client sought a flexible and agile partner capable of adapting to a complex project and ever-evolving coordination.
Zero-C proposed an innovative solution by installing a centralized refrigeration system on the roof of the building, within a custom-built enclosure. We also adapted the timeline to install the piping network before the slab demolition and then divided the project stages so other trades could perform their work without interruption.
- Increased production space with rooftop installation, minimizing work inside the building.
- Simplified coordination, allowing parallel startup with the building renovation.
- On-time delivery, ensuring a quick start for operations in the new building.
Project Specifications
Expertise: Refrigeration for warehouses, packaging rooms, agile and flexible installation, project coordination.
Project Specifications:
- Centralized CO2 refrigeration system installed on the roof
- Parallel compression with high-efficiency compressors
- Adiabatic gas coolers on the roof
- Glycol cooling station for banana rooms
Location: St-Laurent (Quebec), Canada
Installed Equipment
- CO2 refrigeration system (R744) with 274 TR
- Parallel compression compressors
- Adiabatic gas coolers on the roof
- Glycol cooling station for banana rooms